Prairie Ridge Solar

El Paso County, CO
In Development

Project Description

Prairie Ridge Solar, LLC (Prairie Ridge), a Delaware limited liability company and subsidiary of 174 Power Global, is developing the Prairie Ridge Solar Project (Project), a utility-scale solar energy generation facility and battery energy storage system (BESS) located in unincorporated El Paso County, Colorado. The Project area consists of approximately 3,650 acres, of which 2,210 acres are privately owned, and 1,440 acres are owned by the Colorado State Land Board.

While the final site design is in progress, the Project is anticipated to consist of a 400 megawatt (MW) alternating current solar facility and 200 MW/4hour BESS.

Permit Approval Process

A Wind/Solar Energy Overlay (WSEO) permit and a 1041 permit from El Paso County will be required prior to commencing construction of the Project. Prairie Ridge anticipates submitting permit applications by the end of this year.

As part of the approval process, El Paso County will hold public hearings in which members of the audience will get a chance to provide comments related to this Project. El Paso County will be sending notices with time and location of the hearings at the appropriate time.

Adjacent landowners and residents will also have the opportunity to provide public comments in writing to the El Paso County Planning and Community Development Department.

Project Location

Prairie Ridge Solar Location Map 7 3 25 Final pdf

Preliminary Site Layout and Proposed Haul Route

Proposed Prairie Ridge Solar Layout Public Event 7 8 25 pdf

First Neighborhood Meeting

174 Power Global will be hosting its first Open House to learn more about the Prairie Ridge Solar Project. Project representatives will be available to share information, answer questions, and gather input.

Event details:

  • Date: Tuesday July 22, 2025
  • Time: 4:30pm – 6pm
  • Location: Miami-Yoder School
  • 420 S. Rush Rd, Rush, CO 80833

Timeline*

Key MilestonesTime frame
Completion of Site Surveys and StudiesQ4 2025
WSEO / 1041 Permit ProceduresQ4 2025 – Q2 2026
Interconnection StudiesQ2 2025 – Q4 2027
ConstructionQ1 2028 through Q2 2029
Project Completion and In-Service dateQ3 2029

(*) Subject to change

Resources:

Contact Info

174 Power Global  | 400 Spectrum Center Dr., Suite 1400 Irvine, CA 92618

E: emily.bitler@174powerglobal.com | T: (833) 461-7474

Share the Post:

Want to know more about 174 Power Global & our renewable energy solutions?